In ERCOT’s new interconnection process for large loads, a data center can connect sooner as a provisional controllable load resource. That is, ERCOT can curtail power above an agreed firm level. A study from Base Power and Piq Energy shows batteries near the transmission lines to a data center could stand in for most of that curtailment.
In the study, 80 megawatts of batteries would clear every transmission constraint created by a 100 MW data center near Burleson, Texas, on Oncor’s system. A battery beside a strained line relieves it about one-for-one, while curtailing a more distant data…