Delays, delays, delays. It takes forever to build the transmission lines that carry power from where it's produced to where people use it.

Idaho Power and PacifiCorp can tell you. The two utilities thought they'd be starting construction back in 2018 on the Boardman-to-Hemingway (B2H) transmission line, which spans 290 miles of Idaho and Oregon. The project broke ground this summer, 19 years after the utilities initially proposed the project.

Puget Sound Energy (PSE) can tell you. It flipped the switch on its 16-mile Energize Eastside transmission line upgrade project in 2024, a full six…

Weboldal: sightline.org

Élőben, az elmúlt órában: 13 391 dal, 6 035 állomás, 130 ország

Fedezd fel a világot a rádión keresztül

További felfedezési lehetőségek (7)

Hallottál valami jót? Mentsd el, vagy nyisd meg rögtön a Spotifyban.

★ Artist of the week The fastest riser on the radio this week
Your song here? From € 9 per week →
Faith 1190 WNWC AMHallgatás folytatása