On the evening of July 10, 2024, a transmission line in Northern Virginia faulted, and about 1,500 MW of load dropped off the grid. None of it was homes. None of it was factories. All of it was data center load. It has happened twice more in the same zone — most recently on July 22, 2026, when PJM put the load reduction at 3,800–3,900 MW, the largest of its kind in PJM's history.
AI training makes the problem worse. In a normal data center, thousands of unrelated jobs average each other out. AI training doesn't work that way — the GPUs compute together and pause together, so their power…