Mortenson's published case study on Kaiser Borsari Hall at Western Washington University offers one of the more detailed cost-and-schedule breakdowns to come out of a mass timber academic project. The $55 million, four-story building came in $2 million under budget and 25% faster than the original schedule — and the mechanisms behind both figures are directly applicable to developers and GCs evaluating mass timber on future projects. Key Takeaways: Mass timber's lighter structural load allowed the team to eliminate the basement entirely, unlocking $2M in savings — the single largest cost...