Shownotes
ERCOT now has roughly 445 gigawatts of large loads asking to connect to the Texas grid, a figure so large that Joshua Rhodes says it might as well be infinite, because the system cannot physically build for all of it.
To sort real projects from speculative ones, ERCOT is launching a new screening process called batch zero, and stakeholders voted to advance it at last week’s Technical Advisory Committee meeting. On this episode, Rhodes walks through the mechanics with Tiffany Wu, an energy markets and regulatory consultant at McAdams Energy Group and a former adviser to Public Utility…
Website: texasenergyandpower.com